Upcoming Capital Projects

Houston Airports has a five-year capital improvement program (CIP), approved by the City of Houston City Council, which calls for $2.5 billion of spending through fiscal year 2025. The capital improvements are concentrated in terminal and airfield projects with the majority dedicated to George Bush Intercontinental Airport. An updated CIP is approved annually by the Houston City Council as part of each new fiscal year. This CIP was approved on June 24, 2020 by City Council.

Click here to download the latest Houston Airports 5-Year CIP summary.

IAH Upcoming CIP Map

 

IAH CIP Map

HOU Upcoming CIP Map

 

HOU CIP Map

EFD Upcoming CIP Map

 

EFD CIP Map

Upcoming CIP Projects

Project No Location Phase Project Description Estimated Date Estimated Budget (000)
546 IAH DB UPGRADE & RELOCATE APM FACILITIES 1/1/2022 29,870
546A IAH C APM FACILITIES - REPLACE 2 CARS 10/1/2023 14,632
604A IAH C SUBWAY DESIGN 3/1/2022 33,575
618A IAH C TUNNEL DRAINAGE IMPROVEMENTS (WATER ISSUES) 8/1/2021 2,318
646A IAH C TAXIWAY RA,RB,SA,SB - CONSTRUCTION (Phase 1,2 & 3) 6/1/2021 65,632
653 HOU C NORTH ELECTRICAL UPGRADES 6/1/2024 5,217
668 IAH C REHABILITATE & EXPAND ARFF STATION 92 1/1/2022 12,000
669 HOU C REHABILITATE & EXPAND ARFF STATION 81 6/1/2022 11,880
672 HOU C HOBBY DRAINAGE - ROADWAY FLOODING 7/1/2025 3,342
673 IAH DB TERMINAL A MODERNIZATION PROGRAM  12/1/2021 242,800
673A IAH C TERMINAL A OUTBOUND BHS OPTIMIZATION - (Phase 1, 2 & 3) 12/1/2020 37,062
673B IAH C TERMINAL A DOMESTICE EXPANSION  10/1/2021 261,000
673C IAH DB TERMINAL A EARLY & ENABLING 3/1/2022 43,000
673D IAH C TERMINAL A AIRLINE (CARRIER) RELOCATION 3/1/2022 9,000
686 IAH C IAH STORM WATER POLLUTION CONTROL SYS - ENVIRON LIFT ST 7/1/2021 22,603
733 EFD C T-HANGER RAMP AND TAXIWAY D PAVEMENT REHAB 7/1/2025 1,463
735A IAH C IAH EXIT LANE TECHNOLOGY - MULTI -YEAR 7/1/2025 1,580
735B HOU C HOU EXIT LANE TECHNOLOGY - MULTI-YEAR 7/1/2025 1,596
770 HOU C HOU NON-STANDARD FAA TAXIWAYS 3/1/2021 27,843
770B HOU C EARLY DEMOLITION OF 17/35 PAVEMENT 12/1/2020 9,751
773 HOU C TAXIWAY M REHAB 7/1/2023 16,298
775B HOU C RELOCATION OF TSA & HPD BUNKER & K9 7/1/2021 3,100
784 HAS C PUBLIC WI-FI EXPANSION INTO CONCESSION AREAS 12/1/2020 3,296
793 HAS C IAH AIRPORT OPERATIONS CENTER 2/1/2022 3,387
794C HAS C TERMINAL C & TERMINAL C GARAGE WAYFINDING 1/1/2021 4,945
822 IAH DB ENABLING UTILITIES - LANDSIDE 7/1/2021 41,661
826 IAH C MLIT - TERMINAL, AIRSIDE, LANDSIDE 12/1/2020 296,595
828 IAH C FIS CAPACITY EXPANSION  7/1/2021 387,717
907 IAH C REHABILITATION OF TAXIWAY NA 11/1/2020 25,000
907 IAH C REHABILITATION OF TAXIWAY NA 9/1/2021 25,000
921 HOU C HOBBY CONRAC - PLANNING DESIGN CONSTRUCTION 7/1/2021 203,683
922 IAH C ARFF AFFF COLLECTION FACILITY 1/1/2022 7,787
927 HOU C HOBBY VEHICLE FUELING STATION 1/1/2022 1,086
931 IAH C IAH FLYOVER BRIDGE RECONSTRUCTION (RP) 2/1/2021 8,500
932 HOU C 7 GATE EXPANSION AT HOBBY 1/1/2022 234,000
933 IAH C TERMINAL B PHASE III APRON 7/1/2023 176,500
934 HOU C RECONSTRUCT TAXIWAY C AT HOBBY 7/1/2023 37,000
935 IAH C CONSTRUCTION OF KENSWICK INTERSECTION 7/1/2021 3,000
936 HOU C HARDEN AOA PERIMETERS 7/1/2022 2,000
937 HOU O CCTV UPGRADES AT HOBBY AIRPORT - IT  (R&R) 2/1/2021 1,200
A420 HOU C AMS-TAXIWAY G, K, K1 , K2, L & R REHAB AT HOBBY AIRPORT 7/1/2023 7,439
A432 HOU C PASSENGER CONVEYANCE SYS, FIRE PROTECTION SYS, HVAC & UTILITIES REHAB AT HOU 7/1/2024 6,614