Houston Airports has a five-year capital improvement program (CIP), approved by the City of Houston City Council, which calls for $2.05 billion of spending through fiscal year 2022. The capital improvements are concentrated in terminal and airfield projects with the majority dedicated to George Bush Intercontinental Airport. An updated CIP is approved annually by the Houston City Council as part of each new fiscal year. This CIP was approved on June 28, 2017 by City Council.

 Click here to download the latest Houston Airports 5-Year CIP summary.

IAH Upcoming CIP Map

HOU Upcoming CIP Map

EFD Upcoming CIP Map

Upcoming CIP Projects

Project No Location Phase Project Description Estimated Date Estimated Budget (000)
546 IAH DB UPGRADE & RELOCATE APM FACILITIES 8/1/2019 29,000

618A

IAH

C

TUNNEL DRAINAGE IMPROVEMENTS (WATER ISSUES)

10/1/2019

2,250

646A

IAH

C

RECONSTRUCT TAXIWAYS RA, SA & SB

7/1/2020

66,950

646D IAH C AMS - TAXIWAY RB EAST PANNEL REHAB - PRIORITY - IAH 7/1/2020 2,794

668

IAH

C

REHABILITATE & EXPAND ARFF STATION 92

1/1/2020

10,403

669 HOU C REHABILITATE & EXPAND ARFF STATION 81 6/1/2021 1,857
672 HOU C HOBBY DRAINAGE - ROADWAY FLOODING 6/1/2019 3,245

673

IAH

DB

TERMINAL A MODERNIZATION PROGRAM

12/1/2019

196,761
673 IAH C TERM A MODERN - ADDITIONAL RESTROOMS & TERM CURBSIDE 12/1/2020 18,000
673B IAH C DOMESTIC EXPANSION - TICKET COUNTERS, FF&E, BAGGAGE SYS 6/1/2020

15,000

673B IAH C DOMESTIC EXPANSION - CONTRUCTION (GATES + PAVEMENT) 6/1/2021 310,000

686

IAH

C

IAH STORM WATER POLLUTION CONTROL SYS - ENVIRON LIFT ST

12/1/2019

5,204
735A IAH C IAH EXIT LANE TECHNOLOGY - MULTI-YEAR 12/1/2019 5,580

735B

HOU C HOU EXIT LANE TECHNOLOGY - MULTI-YEAR 8/1/2020 1,530

740

IAH

C

IAH FLEET MAINTENANCE BUILDING

9/1/2019

15,586

749

IAH

C

TERMINAL A & B PAVER REMOVAL AT IAH

9/1/2019

2,472
762

IAH

C

INTERNAL SIGNAGE - TERMINAL B NORTH/TERMINAL C SOUTH

7/1/2019

3,045

768TD

IAH

O

COMMON USE TICKET & GATE CHECK-IN COMPUTER SYS - TERM D

7/1/2019

1,277
770 HOU C HOU - NON-STANDARD FAA TAXIWAYS 12/1/2019 13,390
781 HAS O ON CALL TECHNOLOGY CONTRACTS 9/1/2019 4,500
783A IAH O PARKING REVENUE CONTROL SYSTEM AT GBIAH 9/1/2019 7,859
783B HOU O PARKING REVENUE CONTROL SYSTEM AT HOU 9/1/2019 5,501
784 HAS C PUBLIC WI-FI EXPANSION INTO CONCESSION AREAS 9/1/2019 3,296
793 HAS C DATA CENTER-NETWORK & CLOUD REDUNDANCY 9/1/2019 3,193
794 HAS C WAYFINDING GARAGE FACILITIES AT IAH/HOU 9/1/2019 1,900
822 IAH DB ENABLING UTILITIES - LANDSIDE 11/1/2020 37,691
826 IAH C MLIT - TERMINAL, AIRSIDE, LANDSIDE 7/1/2020 184,183

828

IAH

C

FIS CAPACITY EXPANSION

8/1/2020

170,843

835

IAH

C

ROADWAY REHABILITATION

1/1/2020

5,000

835

IAH

C

ROADWAY REHABILITATION

1/1/2021

37,515

901

IAH

C

TAXIWAY WB RECONSTRUCTION 6/1/2020 54,854
908 HAS O IDENTITY MANAGEMENT SYSTEM (IDMS) 8/1/2019 2,000
914 IAH C TERMINAL C GARAGE ADDITIONAL PARKING DECKS 7/1/2020 18,000
915 IAH C REHAB TERMINAL B CONTRACT GARAGE 7/1/2020 5,333
917 HOU C HOBBY CONSOLIDATED MAINTENANCE COMPLEX 10/1/2020 8,550
919 HOU O REPLACE CARPET WITH TERRAZZO TILE IN CENTRAL CONCOURSE 7/1/2019 1,717
922 IAH C ARFF AQUEOUS FIRE FIGHTING FOAM COLLECTION FACILITY 8/1/2020 7,560