PROJECT: PAVEMENT & ROADWAY REPAIRS AT IAH-HOU-EFD [ 460B ]

SUMMARY
Project Name PAVEMENT & ROADWAY REPAIRS AT IAH-HOU-EFD

Project Number 460B

Location HAS

SCOPE
This project will address repairs on isolated areas of distressed airfield pavements observed under the HAS pavement maintenance program on areas of pavement within the operating environment ofRW-15R/30L. The work will include removal, disposal, and replacement of concrete surface pavement and base material, joint sealing, pavement marking, and pavement grooving. Address repairs to RW-15R runway status light system. This work will include removal and replacement of runway status lights and surrounding distressed pavement. The system is operated by the FAA. The FAA will fund the repairs. In addition it will apply sealant in pavement cracks on TW-NA and TW-RA. Rehabilitate the pavement surface on TW-SA. The asphalt surface course is distressed and aircraft operations have been limited. PN460B will remove the asphalt and replace it with a concrete. Expand the aircraft hold apron adjacent to TW-'WW'. The hold apron allows short term queuing for departing aircraft and can currently accommodate regional jet and smaller aircraft only. The expanded the apron will be capable of accommodating ADG IV aircraft and will enhance operations on the airfield.

SCHEDULE
Bid Advertise 11/1/2012

Big Opening Date 2/7/2013

Estimated Duration 194 days
BUDGET
Construction Budget $4,918,000

Construction NTP Date 4/3/2013

CONTACT INFORMATION

Houston Airport System
16930 JFK Boulevard
Houston, Texas 77032

281-233-3000 - phone

281-233-1874 - fax

Design PM
JOHN BUSH
281-233-1039


Construction PM
JOHN BUSH
281-233-1039