» » Upcoming Projects
Upcoming CIP Projects
The following is a listing of upcoming projects for the Houston Airport System. Each project is identified by project number (first column), and related CIP numbers (2nd column) that correspond to the City of Houston’s Capital Improvement Program. The 3rd column indicates the location of the project; George Bush Intercontinental Airport (IAH), William P. Hobby Airport (HOU), Ellington Field (EFD), or System Level (HAS). The fourth column depicts the phase of the project (D = Design, C = Construction, O = Other, DB = Design Build, CM = CM at Risk). The spreadsheet gives a brief description of each component CIP. The sixth column lists the projected date for RFQ/Bids for this Project.
Please remember the construction advertisement dates are approximately four months ahead of the construction appropriation (Council action) date and design requests for proposal are approximately six months ahead of the design appropriation date.
The timing and budgets for the projects listed are subject to change at any time due to scheduling conflicts, availability of funding or scope modification.
|
Project No
|
Loc
|
Phase
|
DESCRIPTION
|
Projected RFQ/BID Date
|
Budget
|
|
647
|
IAH
|
C
|
Reconstruction of Taxiway NB: Construction of the new Taxiway NB, which includes a geometric design and pavement strength required to accommodate Airplane Design Group VI Aircraft.
|
2nd Qtr 2013
|
37,000,000
|
|
685
|
HOU
|
D
|
Hobby Roadway Relocation: Relocation of a portion of the inbound Terminal Roadway at Hobby to accommodate the New Parking Structure to be located west of the existing parking structure. This will also include the relocation of major utility lines.
|
2nd Qtr 2013
|
1,000,000
|
|
565
|
IAH
|
C
|
Landside Roadway Rehabilitation: Reconstruction and/or miscellaneous repairs to North and South Terminal Roads from Terminal A to Terminal C and to the Terminal Road connectors at George Bush Intercontinental Airport. Enhance roadway structure and vertical
|
3rd Qtr 2013
|
12,000,000
|
|
597A
|
HOU
|
C
|
New Hobby Garage/Elevator Replacement: Building a new Parking Garage and Replacement of Garage elevators at Hobby
|
3rd Qtr 2013
|
52,000,000
|
|
634
|
IAH
|
C
|
Terminal A Vault Replacement: Vault replacement on the south side, between the Terminal A Core and the Terminal A/B Garage. Add a generator sized to serve the Terminal A cirtical loads.
|
3rd Qtr 2013
|
11,604,000 |
|
711
|
IAH
|
D
|
Remote Parking Lot (ECOPARK2): Development of new remote surface parking lot in the area between Colonel Fisher and Lee Road. This new remote parking lot will be sized to accommodate approximately 3,000 vehicles.
|
3rd Qtr 2013
|
1,000,000
|
|
674
|
IAH
|
C
|
Taxiway and Roadway Bridges: Design and Construction of repairs to 20 priority structures analyzed in previous study. Repairs of pavement on both inbound and outbound lanes on John F. Kennedy Boulevard, under Taxiway Bridge. Repair/Replacement of damange
|
4th Qtr 2013
|
700,000
|
|
466
|
IAH
|
C
|
Terminal A Garage Level: Reseal Concrete & Expansion Joints - Terminal A 3rd & 4th levels will undergo resealing with new concrete, painting and power washing. Replace expansion joints on the T-A upper u-ramp on the north and south ends.
|
July 2014
|
6,000,000
|
|
618
|
IAH
|
C
|
ITT Level Expansion Joint and Drainage Rehabilitation - Interterminal Train Tunnel (ITT) Rehabilitation: The first phase includes the professsional services for existing condition evaluation and design for emergency reapir of the tunnel. The second phase
|
2nd Qtr 2014
|
5,000,000
|
|
651
|
IAH
|
C
|
Reconstruction of Taxiway WA & WB: Reconstruction of the portion of WA and WB that are exhibiting excessive cracking after the construction of the Concrete Bonded Overlay in 2013. It will also include the widening of Taxiway WA and several connecting tax
|
April 2014
|
30,000,000
|
|
692
|
HOU
|
D/C
|
New Central Plant at HOU: The new Satellite CUP, sized for future expansion and installation of complete thermal production and distribution facilities, will initially house heating system, boilers, piping and distribution pumps to provide adequate heating
|
Jan 2014
|
10,000,000
|
|
712
|
IAH
|
C
|
Terminal C South Apron Lighting Pole Replacement: Existing twenty two (22) light poles are showing signs of corrosion and metal failure around the base of the light pole.
|
Jan 2014
|
1,500,000
|
|
714
|
IAH
|
C
|
Electrical Improvements at Terminal B and C: This project will focus on critical infrastructure, likely located in Terminal B, Terminal C East and the West Baggage Electrical Vaults. This includes completion of phased design in support to follow on capital
|
June 2014
|
750,000
|
|
699
|
IAH
|
D/C
|
Sanitary Sewer Improvements at IAH: Rehabilitation of sanitary main lines (8" thru 18") manholes, cleanouts and force mains at Bush IAH
|
Dec 2013
|
9,600,000
|
|
686
|
IAH
|
O
|
Environmental Lift Stations: To optimize the performance and reliability of IAH's existing Oil/Water units and Environmental Stations.
|
Dec 2013
|
500,000
|
|
466
|
IAH
|
C
|
Terminal B Third and Fourth Levels : Reseal with new concrete. Remove existing rubber membrane over expansion joints on 4th level and re-secure after work on surface is complete. Protection of existing expansion joints.
|
1st Qtr 2015
|
6,000,000
|
|
696
|
IAH
|
O
|
700 Hz Radio - IAH Distributed Antenna System (DAS): Upgrading 700Hz Radio System to allow HAS police and fire fighting personnel to have radio contact while working inside the terminal buildings at IAH
|
Jan 2014
|
8,000,000
|
|
631
|
EFD
|
C
|
Power line Relocation at EFD: Construction of new duct banks and the relocation of overhead power and communication lines into the underground duck bank.
|
Jan 2014
|
1,000,000
|
|
545D
|
HOU
|
C
|
Airfield and Grounds (A&G) Service Complex Upgrade: Development of new Airport Maintenance building on the south side of Houston Hobby Airport. This complex will accommodate new maintenance facility and fleet shop to include vehicle wash facility.
|
March 2014
|
8,314,000
|
|
628
|
EFD
|
C
|
Extend Challenger Road at EFD: Re-route Challenger from Aerospace to Brantley to provide better car traffic flow, and construct a divided roadway with new street lighting, landscaping and roadway signage.
|
July 2013
|
2,000,000
|
|