Project Detail
|
Project Name
|
MISC. UTILITIES IMPROVEMENTS AT GBIAH
|
|
Project Number
|
638
|
|
Location
|
George Bush Intercontinental Airport [ IAH ]
|
|
|
RCA - This is for the design, replacement and upgrade of the sewer and storm water systema at GBIAH. This project will replace and upgrade two sanitary lift stations at Gates C-45 and D-4, and a storm water lift station located adjacent to the JFK/Will
|
|
RFQ Date
|
2/1/2008
|
|
Bid Advertise
|
1/1/2009
|
|
Big Opening Date
|
2/1/2009
|
|
Estimated Duration
|
199 days
|
|
|
|
|
Design Budget
|
$450,000
|
|
Design NTP Date
|
9/1/2008
|
|
Construction Budget
|
$4,125,000
|
|
Construction NTP Date
|
6/1/2009
|
|
|

|
Houston Airport System
16930 JFK Boulevard
Houston, Texas 77032
|
|
281-233-3000 - phone
|
|
281-233-1874 - fax
|
|
|

|
Design PM
PHI NGUYEN
281-233-1533
|

|
Construction PM
PHI NGUYEN
281-233-1533
|
|
|
|
| |
|
 |
 |
 |
 |
|