Project Detail
|
Project Name
|
OVERLAY RUNWAY 12R/30L
|
|
Project Number
|
619
|
|
Location
|
William P. Hobby Airport [ HOU ]
|
|
|
Overlay Runway 12R-30L including grinding the existing surface, install SAMI and overlay with 5 inches of modified asphalt topping. This project is scheduled for major repairs of asphalt runway at the 10 year interval as predicated by the life cycle ana
|
|
RFQ Date
|
10/15/2004
|
|
Bid Advertise
|
4/1/2007
|
|
Big Opening Date
|
4/26/2007
|
|
Estimated Duration
|
329 days
|
|
|
|
|
Design Budget
|
$2,223,000
|
|
Design NTP Date
|
9/19/2005
|
|
Construction Budget
|
$17,392,000
|
|
Construction NTP Date
|
9/7/2007
|
|
|

|
Houston Airport System
16930 JFK Boulevard
Houston, Texas 77032
|
|
281-233-3000 - phone
|
|
281-233-1874 - fax
|
|
|

|
Design PM
DALE WRIGHT
281-233-1773
|

|
Construction PM
DALE WRIGHT
281-233-1773
|
|
|
|
| |
|
 |
 |
 |
 |
|