PROJECT: OVERLAY RUNWAY 12R/30L [ 619 ]

SUMMARY
Project Name OVERLAY RUNWAY 12R/30L

Project Number 619

Location William P. Hobby Airport [ HOU ]

SCOPE
Overlay Runway 12R-30L including grinding the existing surface, install SAMI and overlay with 5 inches of modified asphalt topping. This project is scheduled for major repairs of asphalt runway at the 10 year interval as predicated by the life cycle ana

SCHEDULE
RFQ Date 10/15/2004

Bid Advertise 4/1/2007

Big Opening Date 4/26/2007

Estimated Duration 329 days
BUDGET
Design Budget $2,223,000

Design NTP Date 9/19/2005

Construction Budget $17,392,000

Construction NTP Date 9/7/2007

CONTACT INFORMATION

Houston Airport System
16930 JFK Boulevard
Houston, Texas 77032

281-233-3000 - phone

281-233-1874 - fax

Design PM
DALE WRIGHT
281-233-1773


Construction PM
DALE WRIGHT
281-233-1773
Copyright © 2004-2009 - Houston Airport System.M:HASProjects2-2|1904D2102D2105|320
All rights reserved | Privacy Policy | Terms & Conditions
Comments or Questions: Comment Form or Email Us
Designed by Derek Consulting and Advarion Incorporated