Ongoing Capital Improvement Projects
PROJECT: EFD AIRFIELD IMPROVEMENTS - DISCRETIONARY FUND [ 614 ]

SUMMARY
Project Name EFD AIRFIELD IMPROVEMENTS - DISCRETIONARY FUND

Project Number 614

Location Ellington Field [ EFD ]

SCOPE
This project will assist the Department in the design and documentation for the rehabilitation of Taxiway H, Taxiway A, and paving of the five (5) grassed islands west of Taxiway H as needed to keep pavement condition at PCI levels as recommended by the

SCHEDULE
RFQ Date 11/15/2002

Bid Advertise 4/21/2006

Big Opening Date 5/25/2006

Estimated Duration 547 days
BUDGET
Design Budget $960,000

Design NTP Date 2/14/2004

Construction Budget $12,325,000

Construction NTP Date 1/2/2007

CONTACT INFORMATION

Houston Airport System
16930 JFK Boulevard
Houston, Texas 77032

281-233-3000 - phone

281-233-1874 - fax

Design PM
PHI NGUYEN
281-233-1533


Construction PM
MOHAMMAD ZAHERI
281-233-1949
Copyright © 2004-2009 - Houston Airport System.M:HASProjects2-2|1904D2102D2105|323
All rights reserved | Privacy Policy | Terms & Conditions
Comments or Questions: Comment Form or Email Us
Designed by Derek Consulting and Advarion Incorporated