Project Detail

Ongoing Capital Improvement Projects
PROJECT: AIRFIELD ELECTRICAL NORTH & WEST - [ 575 ]

SUMMARY
Project Name AIRFIELD ELECTRICAL NORTH & WEST -

Project Number 575

Location George Bush Intercontinental Airport [ IAH ]

SCOPE
This project includes New Taxiway Concrete Pavement, Airfield Electrical and Airfield Drainage work. The original scope calls for extension of Taxiway "NC" from Taxiway "NG" to "NJ". Extra scope approved in 2006 was for mower strips on T/W "NB"

SCHEDULE
RFQ Date 8/23/2002

Bid Advertise 4/1/2009

Big Opening Date 5/1/2009

Estimated Duration 179 days
BUDGET
Design Budget $1,400,000

Design NTP Date 3/29/2004

Construction Budget $2,900,000

Construction NTP Date 8/1/2009

CONTACT INFORMATION

Houston Airport System
16930 JFK Boulevard
Houston, Texas 77032

281-233-3000 - phone

281-233-1874 - fax

Design PM
BEECROFT SHITTU
281-233-1774


Construction PM
BEECROFT SHITTU
281-233-1774
Copyright © 2004-2009 - Houston Airport System.M:HASProjects2-2|1904D2102D2105|427
All rights reserved | Privacy Policy | Terms & Conditions
Comments or Questions: Comment Form or Email Us
Designed by Derek Consulting and Advarion Incorporated